Civil fraud and reconstructed narratives: The Commercial Court draws firm lines in Trafigura v Gupta

Commercial and corporate disputes

The Commercial Court’s recent decision in Trafigura PTE Ltd v Gupta & Ors [2026] EWHC 159 (Comm) provides a helpful illustration of the Court’s approach to civil fraud in the context of complex commodities trading arrangements. Although fact‑specific, the judgment is of broader significant in two respects: first, in its treatment of attempts to recharacterise fraudulent conduct after the event; and secondly, in its emphasis on contemporaneous documentary evidence as the decisive benchmark against which competing explanations must be tested. 

Fundamentally, the case is concerned with responsibility for loss, and the limits that will be imposed upon attempts to shift that responsibility by seeking to reframe fraudulent transactions as merely sophisticated commercial structures.

Fraud presented as commercial structure

The proceedings arose out of a series of nickel “buy‑back” trades between Trafigura and companies owned or controlled by Mr Prateek Gupta. Under these arrangements, Trafigura purchased containerised LME‑grade nickel, held title during transit and resold the cargo at destination for a modest return. The trades were supported by apparently orthodox inspection certificates, bills of lading and insurance documentation.

That appearance unravelled when inspections revealed that many of the containers did not hold nickel at all, but low‑value scrap metal. Trafigura alleged that it had been the victim of a US$500 million fraud involving fabricated cargoes and falsified documentation across multiple counterparties and jurisdictions.

The defendant did not confine himself to a simple denial of dishonesty. Instead, he advanced a positive case that the transactions were never intended to operate as genuine commodity trades, but instead operated as a form of financing arrangement, the economic substance of which rendered the absence of real nickel immaterial. On that basis, it was argued that the claimant had knowingly assumed the relevant risk and could not now seek to displace the resulting losses.

The court’s rejection of a retrospective reconstruction

The Commercial Court rejected that explanation in clear and emphatic terms. Mr Justice Saini found that Mr Gupta had orchestrated a “fraud on a grand scale”, involving systematic misrepresentation to not just Trafigura, but also banks, insurers and logistics providers.

Of particular importance was the Court’s treatment of the defendant’s explanatory narrative, the central difficulty with which was found to be that it  was not merely inconsistent with the objective evidence, but that it depended upon a process of tenuous retrospective reconstruction. The judge held that Mr Gupta had sought to “knit together” fragments of internal communications, taken out of context, to construct a self‑serving account of what the transactions were said to represent. The Court was not prepared to accept that approach. Contemporaneous documentation, commercial logic, and credible witness evidence all pointed in the opposite direction. In such circumstances, the defendant’s explanation was not merely unpersuasive: it was untenable.

The judgment makes clear that, in cases of this kind, the Court will not approach competing narratives on an equal footing merely because each is capable of articulation. Where one account depends on selective reconstruction with the benefit of hindsight, and the other is supported by contemporaneous documentary material, there will be a clear winner. 

Reputational allegations and judicial vindication

The defence strategy also involved the making of serious allegations that Trafigura traders were complicit in the alleged arrangement. The court rejected those claims entirely, finding that the individuals concerned had no knowledge of the fraud and were themselves victims of Mr Gupta’s conduct. Indeed, the Court went even further, making clear findings that expressly exonerated those traders. 

That aspect of the judgment is notable for its recognition of the reputational damage that can flow from unsubstantiated allegations in high‑value fraud litigation. Clear judicial findings on personal responsibility can be as significant as findings on liability, particularly where allegations are aired in a public forum. The Court’s willingness to address such allegations directly, and to reject them clearly where they are not made out, underscores that cynical or speculative assertions of complicity will not be permitted to gain traction. 

Risk allocation and commercial reality

The decision also reinforces the Court’s approach to questions of risk allocation in complex trading structures. 

The defendant’s case depended, in substance, on the proposition that the claimant had agreed to assume the risk of non-existent cargoes. That proposition was inconsistent with both the documentary framework of the transactions and ordinary commercial practice. In particular, there was no contractual or documentary indication that such a risk had been contemplated, let alone accepted. In the circumstances, the Court rejected the notion that a sophisticated commodities trader would knowingly assume the risk of fictitious cargoes without documentation or contractual protections reflecting that reality. 

The judgment confirms that civil law will not lend legitimacy to fraudulent conduct by recharacterising it as commercial sophistication. Where loss flows from systematic deceit, attempts to shift responsibility through creative reframing are unlikely to succeed.

Why the decision matters

Trafigura v Gupta sheds light on how the courts approach complex fraud claims involving sophisticated commercial arrangements. It underlines the importance of reliable, contemporaneous evidence, shows a clear judicial reluctance to accept narratives reconstructed after the event, and demonstrates a willingness to confront reputational harm head‑on where unfounded allegations are made.

The case is also a reminder that documentation which appears formally sound can still conceal serious risk. Civil proceedings are not a means of recasting events to avoid responsibility: where fraudulent conduct is presented as commercial ingenuity, the court will look past form and examine the underlying reality.

Beyond reach: High Court draws the line on non-party freezing orders

Commercial and corporate disputes

The English Court has power to grant wide-ranging and invasive freezing injunctions. But there are limits. Even where there exists a real risk of dissipation, a recent court decision shows that it is likely to be difficult to obtain a post-judgment freezing order over assets held by a third party based abroad. 

Background

So you bring a claim against an English company for payment of significant business loans.

You win and look to enforce that judgment. 

You discover that the company has received large sums of money which could not be accounted for in its financial statements and which had not been retained in its bank accounts. 

Moreover, it appears that payments had been made by the company to associated parties based abroad. There appears to be no proper purpose for those payments, and the recipients do not seek to justify or explain them or suggest that they provided any value in return for the same. 

Further still, you can show that there is a real risk that enforcement of your judgment will be frustrated by dissipation of the assets in question. 

Surely in those circumstances the English court would be willing to grant a freezing injunction against the assets of those foreign associates?

Well, in the recent case of Gilbert v Broadoak [2026] EWHC 153 that’s exactly what happened.

On a without notice application made by the successful claimant following judgment, the Court granted a freezing injunction over the assets of two non-parties that were related to the defendant and were based in Spain.

But when the matter came back before the court at the return date hearing, those foreign parties argued that the English court did not in fact have personal jurisdiction over them. 

The court agreed and the injunction against the Spanish respondents was discharged. 

Decision

Harsh? At first blush maybe, but a closer examination of the decision reveals a sound basis for this outcome. 

It is well established that the English Court can grant a freezing injunction over the assets of defendants to English proceedings. 

Based on the decision in TSB Private Bank International SA v Chabra [1992] 2 All ER, the English court can also grant a freezing injunction against parties that are not themselves defendants in the litigation. This applies to injunctions sought against such non-parties both before and after judgment is made in the proceedings. 

‘Chabra’ injunctions – as they are known – are often granted in circumstances where there is evidence that the foreign party is holding assets for the benefit of the defendant (although it is less well known that such injunctions can be put in place where the third party is merely accountable to the principal defendant for some debt or other receivable, claim or potential claim). As with any freezing injunction though, it will still be necessary in all cases to show that the assets of the third party are still at risk of dissipation. 

The application for an injunction must first be served on the non-party in question. And where they are based abroad it will be necessary to obtain the permission of the court to serve the application out of the jurisdiction. In turn, the applicant will need to show (among other things) that one or more of the jurisdictional gateways as set out in CPR PD 6B paragraph 3.1 is satisfied. 

In the Gilbert case, the claimant argued that five such gateways were satisfied. The Court disagreed on each occasion. In particular, the claimant relied on:

  • Gateway 2 which applies where ‘a claim is made for an injunction ordering the defendant to do or refrain from doing an act within the jurisdiction’. This was rejected by the Court: gateway 2 does not apply to an interim freezing injunction. The term ‘injunction’ in the rule refers only to an injunction sought as final, substantive relief.
  • Gateway 3 which applies where ‘a claim is made against the defendant on whom the claim form has been or will be served and – (a) there is between the claimant and the defendant a real issue which it is reasonable for the court to try; and (b) the claimant wishes to serve the claim form on another person who is a necessary or proper party to that claim’. This might have worked had the Chabra injunction been sought at the start of the proceedings. But here the claim against the defendant had already been tried and determined. The possibility that a common issue might arise at some point in future was held to be insufficient to invoke gateway 3.
  • Gateway 10 which applies where ‘a claim is made to enforce any judgment’. This was rejected on the basis that a freezing injunction is not enforcement of a judgment but merely a remedy to prevent the right of enforcement from being rendered ineffective by the dissipation of assets against which the judgment could otherwise be enforced.
  • Gateway 20 which applies where a claim was made ‘under an enactment which allows proceedings to be brought’ and those proceedings were not covered by any of the other gateways. The claimants argued that the application should pass through gateway 20 because it was a claim made under the Senior Courts Act 1981 s.37 which empowers the court to make interim or final injunctions. Again, this was rejected: the phrase “an enactment which allows proceedings to be brought” meant an enactment which established the procedural right to bring proceedings. The fact that a claim or application might be connected with or dependent in some way on an enactment – e.g. s37 – was not sufficient to engage gateway 20. 

On this basis it was held that the Court did not have jurisdiction over the Spanish non-parties. As such, the freezing order against them was discharged. 

The decision is understood to be under appeal.

Key takeaways

So a possibly surprising outcome, but the Court was clearly constrained by the limitations of the jurisdictional gateways in question. Indeed, it is notable that the Judge in the Gilbert case concluded as follows: “It may seem harsh that the Claimants have a good claim in principle to freezing relief against the Respondents…..but no apparent route to establish jurisdiction. However, as Foxton said in Commercial Bank of Dubai…., ‘if there is to be a general power to serve proceedings out of the jurisdiction to assist the enforcement of an English judgment debt, that is a matter for the Rules Committee’”.

Parties faced with cases involving assets by foreign non-parties may well wish to look for alternative ways in which to prevent dissipation. This may include seeking a Chabra injunction at the start of the litigation (in order to engage gateway 3) or even seeing if the facts support the Chabra respondent being added as a party to the claim (for example, on the basis of knowing receipt) and being made subject to a freezing injunction in the usual way.

Ultimately, timely and strategic action at the very outset can often prove decisive in preserving assets and safeguarding the integrity of a claim.

To learn more about our Commercial Disputes expertise and how we can help you, click here.

Building Liability Orders before trial: TCC raises the stakes in Crest v Ardmore

Real estate disputes

 

In Crest Nicholson Regeneration Limited v Ardmore Construction Limited [2026] EWHC 789, the TCC handed down one of the most important Building Safety Act decisions to date, granting two Building Liability Orders (BLOs) against companies associated with an insolvent contractor.

What happened?

Crest Nicholson Regeneration Limited (Crest) engaged Ardmore Construction Limited (ACL) to design and build a residential development in Portsmouth. Post‑Grenfell investigations identified serious fire safety defects in the external wall system. Crest referred the dispute to adjudication. The adjudicator held that the defects amounted to breaches of the Building Regulations and the Defective Premises Act 1972 and awarded Crest £14.9m. ACL entered administration the day before the decision was made and ultimately did not pay.

The application

Crest applied for:

  • an anticipatory BLO, making ACL’s associated companies jointly and severally liable for any liability later established against ACL; and
  • an adjudication BLO, making those associates liable for the unpaid adjudicator’s award.

The decision

The Court granted both BLOs, holding that:

  • BLOs can be made before trial, even where liability is disputed;
  • An adjudicator’s decision can be a “relevant liability” under the Building Safety Act;
  • ACL’s insolvency, group restructuring to ring‑fence liabilities, and the associates’ long‑standing knowledge of the claims all pointed strongly towards it being just and equitable to make the orders; and
  • The Court had a “high degree of confidence” that ACL would ultimately be found liable for the defects. 

Why this matters?

  • Associated companies can face early exposure, even before liability is finally determined.
  • Corporate restructuring and insolvency will not prevent liability being passed up to the group.

Grenfell Tower Inquiry: update on recommendations

Real estate disputes

In September 2024, the Grenfell Tower Inquiry published its final report which made 58 recommendations based on its findings and in our original article we looked at some of the key recommendations affecting the construction industry. We now take a look at the Government’s response to two of those recommendations: 

  • to review the definition of Higher-Risk Buildings; and
  • to convene an advisory panel to produce an authoritative statement on the knowledge and skills to be expected of a competent fire engineer. 

Review of the definition of Higher-Risk Buildings

The concept of a Higher-Risk Building (“HRB”) was introduced by the Building Safety Act 2022 (“BSA”) which contains onerous obligations governing the design, construction and occupation of HRBs. 

In England, the current definition of an HRB is a building which: 

  • is at least 18 metres in height, or has at least 7 storeys;
  • contains at least 2 residential units; and
  • does not comprise entirely of a secure residential institution, a hotel, or military barracks, and does not contain military accommodation. 

For Part 3 of the BSA (design, construction, and building work to existing higher-risk buildings), hospitals and care homes are HRBs, but, under Part 4 (in-occupation duties), they are not. 

As part of the review of this definition, the Government directed the Building Safety Regulator (“the Regulator”) to carry out a review of the key factors in the HRB regime and their implications. Following consideration of the available evidence, the conclusion published in December 2025 was that the original definition “still seems focused on the appropriate categories of buildings”, and that an increase to the scope of the HRB regime at this time would not be right. It was also noted that the definition of HRB, and the associated regime, has only been in operation since April 2024 and so it is still early to say whether it needs to be changed, albeit it is already having a positive impact on buildings within its scope.

Despite this, the Government and the Regulator acknowledged the importance of work to protect vulnerable residents as well as the evolving risks of the built environment and agreed that the Regulator will operate a process for ongoing risk-based review of the definition. 

The conclusion is in quite stark contrast to the Inquiry’s finding that defining an HRB by reference to height is unsatisfactory and arbitrary, with the nature of its use and the presence of vulnerable people being more relevant than height. The material tension between the ideal approach, and an approach that is workable in practice, is manifest in this result, and it seems the Government has fallen on the side of practicality so as not to further stifle development in the UK, particularly in the residential sector. 

Authoritative statement 

In response to this recommendation, the Government appointed a panel comprised of eight of the foremost experts, which produced the authoritative statement in December 2025. 

The panel set down the following definition for a fire engineer:

Fire engineers are professionals who develop and deliver engineering solutions that protect people and mitigate harm to the built and natural environment in the event of fire.” 

The statement observed that there is no single recognised pathway to becoming a fire engineer, which leads to variation in the qualifications and skills of those operating as fire engineers. Further, ethical standards are inconsistently defined and monitored, and engineering principles are not always effectively applied, which leads to issues with delivery and poor confidence in the profession.

The statement confirms the panel’s support for the Government’s intention to regulate both the title and function of fire engineers and required legal restrictions on the use of the title of fire engineer. Further, statutory regulation should define the functions and activities that can be performed only by an individual who is registered and has met specific requirements. The preparation of the fire strategy should be a protected function, as that is the fundamental core of a fire engineer’s work. In the absence of an existing authoritative definition of what a fire safety strategy is, the statement sets out the panel’s view on what a fire safety strategy should include, and notes that “In delivering the fire safety strategy, the role of the fire engineer is fundamentally one of integration. The fire engineer acts as the link between multiple disciplines”.

The Government has achieved a robust delivery of this recommendation, with the panel’s statement and the Government’s intentions being aligned, which will hopefully motivate the Government. The stumbling block will be the timeline for the Government to turn intention into reality, and whether the practical reality of the huge demand for fire engineers will lead to the Government diverging from the panel’s statement and its current intention.